In this phase, we are asking some questions about two different bus network concepts. These concepts are intended to help CAT better understand what is most important for providing transit service for the community.
Comments from FHWA and EPA to the Draft DEIS have been received
June 2019 Update
The revised Draft EIS was submitted to GDOT for review on June 7, 2019
Another project milestone, the Preliminary Field Plan Review, has been scheduled for June 25 and 26, 2019
The History Assessment of Effects document was concurred with by the State Historic Preservation Office on May 23, 2019
November/December 2019 Updates
The revised Draft EIS addressing FWHA and EPA comments was been submitted to GDOT for review in November.
A few more comments were received from GDOT in late November. They have been addressed and Draft EIS and Response to Comments letter were submitted back to GDOT in December.